The price will come later
Kevin Warsh has been chairing the Fed since May. On September 29, he promised this guaranteed price cap. He wants it “promptly.”
The general contractor submitted its proposal in January. It totals $2.135 billion. According to the inspector general’s report, $2.078 billion had already been allocated.
In August, the board was still hesitant to sign. “Almost everything had already been awarded,” he told the inspector.
Excavation work was carried out beneath the buildings near the Potomac River. Water was seeping in. The ground was unstable. The excavation was “complicated and costly,” the inspector writes.
Roof Gardens
The push began in the summer of 2025. In July, Russell Vought wrote to Powell. He oversees the White House budget. He took aim at the decor. His letter targeted “rooftop terraced gardens,” CBS News reported. It also targeted VIP dining rooms and “high-end” marble.
A Cost Estimate Presented
That same month, Bill Pulte urged Congress to investigate Powell’s testimony. Pulte heads the federal housing finance agency. According to CBS News, he accused Powell of being “misleading.” He provided no evidence.
Subpoenas, Then a Judge
In January 2026, Powell reveals a criminal investigation. The Department of Justice is targeting his June 2025 testimony before the Senate. In a video, Powell describes this as “threats” and “pressure” from the administration.
A federal judge then ruled on the matter. He struck down the grand jury subpoenas. CBS News reports that he viewed them as a pretext. According to the ruling, they were intended to pressure Powell into lowering interest rates or resigning. The prosecution had produced “virtually no evidence” of a crime, NBC News reports.
On April 24, the Washington, D.C., U.S. Attorney’s Office closed the investigation. It handed the matter over to the inspector general. The way was cleared for Kevin Warsh.
No Crime Found
Michael Horowitz’s report was released on Wednesday. The Fed’s inspector general dated it September 29. Powell had requested it in July 2025.
The inspector general’s team found no reasonable basis to believe a federal crime had been committed. It found no administrative misconduct.
Later on Wednesday, Trump named a culprit on Truth Social. “It’s Jerome Powell’s fault.” He wants Powell to be “forced to resign, IMMEDIATELY.” He wants the government to prosecute him, failing that, “for corruption or incompetence.” He wants Attorney General Todd Blanche to review the report and make a decision.
My side is the one that sets the price before signing. Powell’s counsel signed first. Trump is demanding a trial. The report recommends a cap.
There’s no crime. No price cap either.
Mismanagement
On Wednesday, according to CNN, White House spokesperson Kush Desai spoke of “blatant mismanagement.” The report documents it.
The inspector concludes that the board did not manage its contract effectively. It deviated “on numerous occasions” from its cost-control provisions.
A $1.5 million contract
The board had, however, chosen a protective approach. The general contractor is involved from the design phase onward. The contractor then commits to a guaranteed maximum price. Beyond that, any cost overruns are the contractor’s responsibility, with some exceptions.
This contract required three detailed cost estimates as the plans progressed. The board did not request any of these estimates. None were provided. The contractor’s first overall estimate arrived with its January proposal. Work had been underway for three and a half years.
A cost cap did exist—on paper. The project team had set it at 857 million. They communicated this to the architect in April 2020. They never updated it. Neither the contractor nor the council representative was informed of it.
Eighty-four lots
The board believed it was protected
The board disputes this. According to its officials, each awarded lot transferred its risks to the contractor. They view this as the equivalent of a guaranteed price. The inspector rules: “We did not find this to be the case.”
Two out of seven bids
The two contracts for mechanical, electrical, and plumbing work on the building’s structural framework, originally estimated at 178 million, were awarded for 539 million.
Seven bidders, two bids
In 2025, two more lots of the same type followed. The four lots total 694 million. That’s nearly 500 million more than the architect had anticipated. Three of the four lots had not received three bids.
The team did not request a second opinion from its representative. They explained that they wanted to “keep the project moving forward.” I consider this decision to be at the heart of the failure.
A lawn on top of a garage
On the plans, the “garden terrace” is part of the south lawn from 1951. It covers the new garage. Small original planters once held herbs there.
According to the project team, the green roofs cost $615,000. The fountains account for $3.4 million in the contractor’s proposal.
Beehives on Other Roofs
On Track, Quarter After Quarter
The dashboards were reassuring. Quarter after quarter, the project was “on track.”
The budget was only flagged as “at risk” for four consecutive quarters. That was just before the 2025 increase.
Planned allocations within the scope of the project weren’t reported to management. Even a batch that was well above the estimate didn’t need to be reported.
Senior executives trusted the facilities team. The inspector refers to oversight “based on trust.”
A cap, even if late
Warsh entrusts management of the project to the General Services Administration (GSA). The GSA manages federal buildings. It will report to the board and its chairman. Its administrator, Edward Forst, promises to get the projects “back on track.”
An auditor to review payments
That leaves the guaranteed price. Warsh himself admits it’s “a late stage.”
What the offensive has produced
On Wednesday, Pirro’s office was already reviewing the report, a spokesperson told NBC.
Remedies, No Prosecution
Based on the evidence, the attack falls flat. I see no action for taxpayers in Wednesday’s messages. They target one man. They don’t save a single dollar.
One building pays for the other
Warsh’s letter refers to “public funds.”
Columnist’s Transparency Box
Editorial Position
Methodology and Sources
This text respects the fundamental distinction between verified facts and interpretive analyses. The methodological rule is consistent: factual information is published only if it is supported by a verifiable source, and the sources actually used in this article are listed under “Sources,” never here.
When an article cites statistical, economic, or geopolitical data, it comes from data-producing institutions (intergovernmental organizations, central banks, national statistical institutes), and the specific institution is listed under “Sources.”
Nature of the Analysis
OPINION: Powell’s Fed has committed $2 billion with no cap, and Trump sees only one culprit
Sources:
Primary Sources:
GSA — The Fed Entrusts the GSA with Overseeing the Renovation of Its Headquarters, October 1, 2026
Federal Reserve — Q&A on the Renovation of Its Two Buildings, updated September 30, 2026
Secondary Sources:
CBS News — No Laws Violated in Fed Renovations, Inspector General Concludes, September 30, 2026
Fox Business — Warsh Tasks the GSA with Completing the Fed’s Renovation Project, October 1, 2026
This content was created with the help of AI.